Table of Contents

Tullyhaw Wind

SHARE

Original planning submission can be found here.

ABP planning submission can be found here.

About The Project

The proposed wind farm development is located in Tullyhaw, Ballyconnell, Co. Cavan. The proposed project is being developed by Natural Forces, who acknowledge that working on these lands is a privilege that comes with a great deal of responsibility. As such, the project, which is approximately 2km northwest of Ballyconnell town could have a total capacity of up to 4.26 MW, representing 1 turbine. This would be enough electricity to power over 3,000 Irish homes each year.

Project Updates

As we develop this project, we are committed to providing the public with frequent updates and the results of our environmental studies in this section.

Project Milestone Timeline

February 2021 – Environmental surveys started
April 2022 – Planning submitted originally to Cavan County Council for an Enercon E115 on a 92m tower with an overall tip height of 149.86 (ref: 22137)
June 2022 – Granted a RESS 2 contract
August 2022 – Wind monitoring began
October 2022 – Planning for the Enercon E115 granted by Cavan County Council
January 2023 – Grid connection plans finalised with a 20kV modular substation
April 2023 – Planning resubmitted to Cavan County Council for an Enercon E138 on a 99m tower with an overall tip height of 169m (ref: 2360009)
June 2023 – Planning for the E138 granted by Cavan County Council
November 2023 to date – Financing stage

Who is proposing this project?

Natural Forces

Natural Forces is an independent power producer that develops, owns, and operates renewable energy projects. Natural Forces was established in 2001 and has its head office in Halifax, NS, as well as regional offices in Chetwynd, British Columbia; Quispamsis, New Brunswick; Dublin, Ireland; and New York State. Collectively, Natural Forces has close to 300 MW of renewable energy projects in operation across Canada, with several ongoing projects at various stages of completion in Nova Scotia, New Brunswick, Prince Edward Island, Labrador, Saskatchewan, British Columbia, Ireland, and New York.

The senior management team at Natural Forces has over 70 years of combined renewable energy experience encompassing all project life cycle activities in a range of international locations including Canada, Ireland, Poland, the UK, and Australia. Natural Forces is an integrated developer and operator of renewable energy assets. The in-house team undertakes all activities from initial site selection, development, financing, construction, operations, and asset management. Our vision is to develop, construct, operate, and own clean renewable energy projects across Canada in partnership with local and Indigenous communities.

Why here?

When developing a wind project, it is crucial to find the most suitable location to host it.  To do so, there are four main factors to consider during the site finding phase of development:

  • Wind resource
  • Distance to existing electrical and civil infrastructure
  • Environmental sensitivity
  • Socio-economic concerns

Ireland has excellent wind resources, so generating electricity is feasible in many locations around the country. Factors other than the strength and consistency of the wind must be taken into account when considering a site, such as proximity to the electricity grid, road access, ecology, archaeology, and cultural significance, proximity to residential dwellings, and health concerns.

The location of the Tulllyhaw Wind was selected after a thorough review of all of these factors.

Community Engagement

Natural Forces is committed to engaging with the public, stakeholders, and stakeholder groups throughout the lifetime of the project. We are both keen to ensure the community understands the project details and is aware of project activities, and to accept input and feedback from community members. Below is information about the major public and stakeholder engagement activities that have taken place to date, including summaries of the information that has been shared at our open houses.

Public Consultation

Public consultation for this project took place Q4 2021. 

What is the process?

1

Development
(Current Stage)

  • Assess the wind resource
  • Survey for environmentally sensitive features
  • Optimize turbine location to capture the wind efficiently and minimize impact on sensitive features
  • Begin consultation with regulators and the public
  • Conduct and present the Environmental Impact Assessment for environmental approval
  • Apply for road, work and construction permits​

2

Construction

  • Clear trees for roads and turbine pads
  • Build access roads and pad areas
  • Pour the turbine foundation
  • Assemble the wind turbine
  • Connect to grid

3

Operation

  • Commission the wind turbines to start producing power
  • Conduct post-construction wildlife monitoring
  • Monitor remotely for real-time alerts when additional maintenance is needed
  • Operate for 30 years​

4

Decommission or Retrofit

  • Assess wind turbine after 30 years
  • Decommission wind turbines in 3-6 months
  • Reclaim the site to its former state OR
  • Receive approvals and permits to retrofit the turbine to continue harnessing energy​

Environmental Impact Assessment

In Ireland any project that exceeds 5MW or 5 turbines are required to complete an environmental impact assessment (EIA). During this process a team of consultants will undertake surveys to evaluate the location and overall impact of the project on the surrounding area. As this project does not exceed 5MW or 5 turbines an EIA is not required. 

With that being said, Natural Forces still carried out an ecological impact assessment (EcIA) for this site which completed surveys for: 

  • Habitats
  • Fauna
  • Birds

 

With these surveys it was concluded that the project will have no adverse impacts on the surrounding ecological environment. 

Frequently Asked Questions

Natural Forces undertakes rigorous environmental impact assessments ahead of construction to determine existing environmental sensitivities and potential impacts on the project to the environment. This information will be reviewed by county councils and will be open for public comment.

The proposed turbines will be set back at least 500m or 4 times overall tip height in line with the WEG 2006 and 2019 respectively.

No. A study carried out by the HSE in 2017 investigated the health effects of wind turbines. This study found there is no support for adverse effects on health from wind turbines. The summary of these results can be reviewed here.

​For this project, Natural Forces leases land from private landowners. Over the course of several years, we have developed trusted relationships with the landowners and in all instances the land remains in the ownership of the landowner and is leased for the duration of the project. No land has been leased from unwilling landowners.

During construction, Natural Forces makes every attempt to hire local contractors, using our in-house construction management company, Natural Forces Construction, to ensure smaller contractors are able to participate. ​

Wind turbines have moving parts and therefore some sound can be expected. However, well-designed wind turbines are generally quiet in operation, and compared to the noise of road traffic, trains, aircraft, and construction activities, to name but a few, the sound from wind turbines is very low. As wind turbine technology has evolved, the sounds emitted have decreased. The further away you are from a project, the less sound it will make. This site will likely have trees and other barriers that would break a lot of the sound before it reaches homes. A typical wind project would have a noise level of between 35-45 decibels. For reference, the compressor of a refrigerator produces 40-45 decibels. Stories of excessive noise often come from areas where the turbines are very close to homes. Natural Forces follows the minimum standards for distance from residences laid out by local regulations.

For more information contact:

Jonathan Coffey, Project Manager
+353876352172
jcoffey@naturalforces.ie

MORE PROJECTS

The initial plans are for the proposed project to consist of an estimated 10-12 wind turbines that will have an installed capacity of approximately 50 MW, enough electricity to power over 17,000 Nova Scotian homes. The project is located in Cumberland County, on Westchester Mountain near Highway 104, approximately 24 km from the Cobequid Pass Tolls.
Welcome to the website for the proposed Wejipek Wind Project! This website was created to provide information to community members, First Nations, government, and other stakeholders about the proposed project. Natural Forces is committed to meeting with stakeholders throughout the lifetime of the project. Open houses and other community engagement activities are planned for this project - the website will be updated as information becomes available.
Welcome to the website for Phase II of the Wocawson Energy Project! This phase has been named the Neweg Energy Project. This website was created to provide information to community members, First Nations of New Brunswick, the government, and other stakeholders about the project. Natural Forces is committed to meeting with rightsholders and stakeholders throughout the lifetime of the project.
This project is located in Mi’kmaki, the ancestral territory of the Mi’kmaq. Natural Forces acknowledges that working on these lands is a privilege that comes with a great deal of responsibility. We believe that private companies have an important role to play in the decolonization of the energy sector and, ultimately, the path towards reconciliation through partnerships and meaningful engagement. To honour and achieve this, we must look forward for generations and integrate the practices and knowledge of the original land stewards, the Mi’kmaq, into project planning.
The proposed Benjamins Mill Wind Project is being developed by a partnership formed between Natural Forces and Wskijnu’k Mtmo’taqnuow Agency Ltd (the Agency), a corporate body wholly owned by the 13 Mi’kmaw bands in Nova Scotia. Together, the partnership will develop, construct, operate, and own the project. The project is located in the West Hants Regional Municipality in Hants County, 14 km southwest of Windsor.
The proposed project will have an installed capacity of up to 50 MW. This represents up to 12 turbines that and could collectively power an estimated 17,000 homes. The project is located in the Pictou County in Piedmont, about 23km east of New Glasgow.