Table of Contents

Neweg Energy Project

SHARE

April 8, 2024 UPDATE:

Full construction activities have begun on site with work on access roads and turbine foundations. Construction activity will continue throughout 2024. If you are accessing the site area, please reach out to us at the contact information at the bottom of this page for a safety briefing.

 

About The Project

Phase II of the Wocawson Energy Project is called the Neweg Energy Project. The Neweg Energy Project is located adjacent to the operational Wocawson Energy Project in Kings County, New Brunswick, approximately 20 kilometers southeast of the Town of Sussex.  Please visit the Wocawson Energy Project website here for more information about that project.

The Neweg Energy Project consists of 6 wind turbines with a collective installed capacity of approximately 25 MW. This size of project represents sufficient electricity generation to power approximately 8,000 New Brunswick homes. It is adjacent to Mitton Road (also known as Armstrong Road), which leads to a network of forestry roads throughout the project site. The original Environmental Impact Assessment (EIA) for the Wocawson Energy Project also evaluated the Neweg Energy Project as a second phase. The environmental impact assessment received approval on July 27, 2020. More information is available in the EIA section of this webpage below.

The Neweg Energy Project will provide a clean, stable source of electricity to help meet growing energy demands in New Brunswick through the generation of emission-free energy. 

Project Milestone Timeline

As we develop this project, we are committed to providing the public with updates and the results of our environmental studies in this section.

July 2020: The project received EIA approval
April 2023: The project received a one-year extension on the EIA approval to start construction activities.
October 2023: EIA approval was granted for minor changes to the access road and equipment laydown area.

November 2023: site preparation activities, such as tree clearing, began on site.

January 2024: The power purchase contract was signed between the project partners and NB Power.

February 2024: A public open house was held on the February 21, 2024, from 4-7 pm at the Penobsquis Fire Hall (12231, NB-114, Penobsquis, NB E4G 2Y).

April 2024: Full construction activities have begun on site with work on access roads and turbine foundations.

 

Who is proposing this Project?

Natural Forces is partnering with the Mi’gmaq United Investment Network (MUIN) to develop, construct, own, and operate the Neweg Energy Project. The project partners announced the partnership and signed the power purchase contract together with NB Power on January 16, 2024. Please see the press release here for more information.

The Mi’gmaq United Investment Network (MUIN)

The Mi’gmaq United Investment Network (MUIN) to develop, construct, own, and operate the Neweg Energy Project. MUIN was created by the Mi’gmag First Nations in New Brunswick as a profit-sharing entity to explore economic opportunities, investments, and partnerships that can produce results for the Mi’gmaq communities in New Brunswick and their members. 
 

Natural Forces

Natural Forces is an independent power producer that develops, owns, and operates renewable energy projects. Natural Forces was established in 2001 and has its head office in Halifax, NS, as well as regional offices in Chetwynd, British Columbia; Quispamsis, New Brunswick; and Dublin, Ireland. Collectively, Natural Forces has close to 300 MW of renewable energy projects in operation across Canada, with several ongoing projects at various stages of completion in Nova Scotia, New Brunswick, Prince Edward Island, Labrador, Saskatchewan, British Columbia, and Ireland.
 
The senior management team at Natural Forces has over 70 years of combined renewable energy experience encompassing all project life cycle activities in a range of international locations including Canada, Ireland, Poland, the UK, and Australia. Natural Forces is an integrated developer and operator of renewable energy assets. The in-house team undertakes all activities from initial site selection, development, financing, construction, operations, and asset management. Our vision is to develop, construct, operate, and own clean renewable energy projects across Canada in partnership with local and Indigenous communities.

 

Project Benefits

The community benefits the project will bring include electricity to power approximately 8,000 New Brunswick homes annually. Produce emission-free electricity that will both increase energy security and displace generation from fossil fuels, thereby reducing greenhouse gas emissions.

  • Provide annual tax revenue to the local and provincial governments over the life of the project.
  • Create local employment and contracting opportunities during the development, construction, operation, and decommissioning phases of the project.
  • Increase own-source revenue to the Mi’gmaq First Nations through project ownership.
  • Contribute to energy security in New Brunswick and displace generation from fossil fuels, thereby reducing greenhouse gas emissions.

Newsletters

Natural Forces has engaged with, and continues to engage with, stakeholders through a number of avenues, including newsletters. Each of the newsletters circulated to date is linked below. Interested in receiving our newsletters?

Sign up here!

Feb 2024 Newsletter 

Open Houses

The Neweg Energy Project has been discussed previously with the community in the open houses for the now operational Wocawson Energy Project. The previously presented information can be found on the Wocawson Energy Project website here.

The project partners hosted a follow-up open house on February 21, 2024, to provide an update on the Neweg Energy Project. A summary of the information displayed at the open house is linked here.

 

What is the process?

1

Development
(Current Stage)

  • Assess the wind resource
  • Survey for environmentally sensitive features
  • Optimize turbine location to capture the wind efficiently and minimize impact on sensitive features
  • Begin consultation with regulators and the public
  • Conduct and present the Environmental Impact Assessment for environmental approval
  • Apply for road, work and construction permits​

2

Construction

  • Clear trees for roads and turbine pads
  • Build access roads and pad areas
  • Pour the turbine foundation
  • Assemble the wind turbine
  • Connect to the NB power electrical grid

3

Operation

  • Commission the wind turbines to start producing power
  • Conduct post-construction wildlife monitoring
  • Monitor remotely for real time alerts when additional maintenance is needed
  • Operate for 30 years​

4

Decommission or Retrofit

  • Assess wind turbines after 30 years
  • Decommission wind turbines in 3-6 months
  • Reclaim the site to its former state OR
  • Receive approvals and permits to retrofit the turbine to continue harnessing energy​

Environmental Impact Assessment

Since the original submission of the Environmental Impact Assessment for Phase I in 2018, initial locations proposed for Phase II were relocated due to additional understanding of the project site and additional regulations from the province. Due to the change in the turbine positions for the Phase II of the project, an addendum to the Environmental Impact Assessment was submitted to the province for review in January 2020. This addendum served to assess the potential environmental impacts of the project at these new locations, the following studies have been completed:

  • Bird and Bat surveys
  • Wetland and Watercourse surveys
  • Vegetation and Habitat Surveys
  • Archeological Assessments


On July 27, 2020 the Phase II Addendum was approved. In summer 2023, additional fieldwork was completed to study minor updates to the project, such as an alternative access road, a laydown area, and slight realignment of the collector lines. On October 12, 2023, EIA approval was granted for these minor updates.
The addenda to the EIA is attached below:

The original EIA submission for Phase 1 can be found here.

Frequently Asked Questions

Natural Forces undertakes rigorous environmental impact assessments ahead of construction for all projects to determine existing environmental sensitivities and potential impacts on the project to the environment. For the Neweg Energy Project, this information was reviewed by provincial government officials and was open for public comment. All of this information is available above.

The proposed turbines will be set back at least 1.0 km from all the houses.

A study done by Health Canada in 2014 investigated the health effects of wind turbine noise. This study found that wind turbine noise was not associated with self-reported sleep, illness, or stress level issues. The summary of these results can be reviewed on the Health Canada Environmental and Workplace Health webpage.

The majority of the Neweg Energy Project infrastructure will be located on provincial Crown land. As such, the project partners have worked closely with the province to use the land for this purpose.

The project partners are also working with a number of private landowners to gain access to certain portions of the project site through Easement Agreements.

During construction, Natural Forces makes every attempt to hire local contractors using our in-house construction management company, Natural Forces Construction, to ensure smaller contractors are able to participate. 

Wind turbines have moving parts and therefore some sound can be expected. However, well-designed wind turbines are generally quiet in operation, and compared to the noise of road traffic, trains, aircraft, and construction activities, the sound from wind turbines is very low. As wind turbine technology has evolved, the sounds emitted have decreased. The further away you are from a project, the less sound it will make. This site has trees and other barriers that would break a lot of the sound before it reaches homes. A typical wind project would have a noise level of between 35-45 decibels. For reference, the compressor of a refrigerator produces 40-45 decibels. (Check out the Energy Nova Scotia Wind Page for more information). Stories of excessive noise often come from areas where the turbines are very close to homes. Natural Forces follows the minimum standards for distance from residences laid out by local regulations, or a typical minimum of 1 km.

For more information contact:

Meg Morris, Project Manager

902-483-9592

community@naturalforces.ca

MORE PROJECTS

The initial plans are for the proposed project to consist of an estimated 10-12 wind turbines that will have an installed capacity of approximately 50 MW, enough electricity to power over 17,000 Nova Scotian homes. The project is located in Cumberland County, on Westchester Mountain near Highway 104, approximately 24 km from the Cobequid Pass Tolls.
Welcome to the website for the proposed Wejipek Wind Project! This website was created to provide information to community members, First Nations, government, and other stakeholders about the proposed project. Natural Forces is committed to meeting with stakeholders throughout the lifetime of the project. Open houses and other community engagement activities are planned for this project - the website will be updated as information becomes available.
Welcome to the website for Phase II of the Wocawson Energy Project! This phase has been named the Neweg Energy Project. This website was created to provide information to community members, First Nations of New Brunswick, the government, and other stakeholders about the project. Natural Forces is committed to meeting with rightsholders and stakeholders throughout the lifetime of the project.
This project is located in Mi’kmaki, the ancestral territory of the Mi’kmaq. Natural Forces acknowledges that working on these lands is a privilege that comes with a great deal of responsibility. We believe that private companies have an important role to play in the decolonization of the energy sector and, ultimately, the path towards reconciliation through partnerships and meaningful engagement. To honour and achieve this, we must look forward for generations and integrate the practices and knowledge of the original land stewards, the Mi’kmaq, into project planning.
The proposed Benjamins Mill Wind Project is being developed by a partnership formed between Natural Forces and Wskijnu’k Mtmo’taqnuow Agency Ltd (the Agency), a corporate body wholly owned by the 13 Mi’kmaw bands in Nova Scotia. Together, the partnership will develop, construct, operate, and own the project. The project is located in the West Hants Regional Municipality in Hants County, 14 km southwest of Windsor.
The proposed project will have an installed capacity of up to 50 MW. This represents up to 12 turbines that and could collectively power an estimated 17,000 homes. The project is located in the Pictou County in Piedmont, about 23km east of New Glasgow.