Welcome to the official webpage of the proposed Salmon River Wind Project!
This website was created to provide project information to Rightsholders and stakeholders of the Salmon River Wind Project (the Project), a wind energy project being proposed by Wolastoqey Resource Developments Inc. and Natural Forces in southern New Brunswick. The Project will play a crucial role in displacing energy produced by fossil fuels from the electrical grid, significantly reducing greenhouse gas emissions and contributing to the fight against climate change.
Information sessions and other community engagement activities are planned for the Project. The website will be updated as information becomes available.
Mailing List
To join the mailing list for the Salmon River Wind Project, please click on the link below and fill out your contact information.
About The Project
Natural Forces acknowledges that New Brunswick is situated on the unceded and unsurrendered territories of the Wolastoqey, Mi’gmaw, and Peskotomuhkati peoples and that working on these lands is a privilege that comes with a great deal of responsibility.
The Project is proposed to be located approximately 9 km southwest of Hammondvale on provincial Crown land. Approximately 34 wind turbines are being permitted as part of the Project’s Environmental Impact Assessment (EIA). The Project’s total installed capacity of approximately 203 megawatts (MW)) would supply enough electricity to power an estimated 43,000 New Brunswick homes annually.
Additional activities related to the Project include the construction of an approximately 36 km overhead transmission line to connect the project to the existing NB Power electrical grid. The transmission line is proposed to be located on a mix of provincial Crown and private land, and its routing is being studied as part of the EIA process.
An EIA is required for the Project with a submission made to the province on September 5, 2025. Pending approvals, pre-construction activities could begin as early as Fall 2026.


Who is proposing this project?
The Project is being developed by a partnership between Wolastoqey Resource Developments Inc. and Natural Forces.
Wolastoqey Resource Developments Inc.
Natural Forces

Natural Forces is a private independent power producer that delivers renewable energy projects in partnership with local communities across Canada, Ireland, and France. Natural Forces develops, constructs, owns and operates wind, solar, hydro and storage projects with Indigenous communities, universities, municipalities, and local community funds. Partnering with local communities for these projects not only generates clean and renewable electricity but delivers local economic prosperity and raises awareness of the challenges of climate change.
Project Update
Complete/Ongoing Work:
- Wind data collection
- Interconnection studies
- First Nation engagement
- Public and stakeholder consultation
- Transportation studies
- Site suitability assessment with turbine manufacturer
- Environmental Impact Assessment field and desktop studies
- Municipal development permitting
- Securing a Power Purchase Agreement
Future Work :
- Environmental Impact Assessment submission and approval
- Pre-construction site activities
- Turbine procurement
- Civil work
- Electrical works and interconnection
- Turbine erection
- Project commissioning
- Site reclamation from construction activities
- Operation of turbines
- Post-construction environmental studies
- Site maintenance and upkeep
- Decommissioning and site reclamation
Project Milestone Timeline
- February 2011 – Wind monitoring began
- August 2023 – Environmental surveys started
- December 2024 – Rightsholders engagement initiated
- April 2025 – First public information session held
- January 2025 – Power Purchase Agreement secured
- February 2025: Interconnection studies commenced (still in progress)
- September 2025: EIA registered with the province
Why here?
The location of the Project offers favorable elevation and a reliable wind resource. The area allows for turbines to be setback at least 1 km from year-round dwellings. Additionally, the proposed site is situated on Crown land in an area that has undergone several generations of forestry and has many existing access roads that can be used for the Project.
Project Benefits
- Provide annual tax revenue to local and provincial governments over the life of the Project.
- Create local employment and contracting opportunities during the development, construction, operation, and decommissioning phases of the Project.
- Increase revenue to local businesses due to economic spinoff from Project activities.
- Produce emission-free electricity that will both increase energy security and displace generation from fossil fuels, thereby reducing greenhouse gas emissions.
- Increase own-source revenue to Wolastoqey Resource Developments Inc. through project ownership.
- Assist the province with its energy strategy of developing 1400 MW of new wind power, outlined in Powering our Economy and the World with Clean Energy – Our Path Forward to 2035.
Public & Stakeholder Engagement
Natural Forces is committed to engaging with the public, stakeholders, and special interest groups throughout the lifetime of the Project. Below is information about the major public and stakeholder engagement activities that have taken place to date, including summaries of the information that has been shared at our information session.
Newsletter
Natural Forces has engaged with, and continues to engage with, stakeholders through a number of avenues, including newsletters. Each of the newsletters circulated to date will be linked below:
Information Session
All of the information that was presented at these Information Session can be seen at the links below:
Public Info Session 1 Handout
Public Info Session 2 Handout
Public info Session 3 Handout
Public Info Session 4 Handout
What is the process?
1
Development
(Current Stage)
- Assess the wind resource
- Survey for environmentally sensitive features
- Optimize turbine location to capture the wind efficiently and minimize impact on sensitive features
- Begin consultation with regulators and the public
- Conduct and present the Environmental Impact Assessment for environmental approval
- Apply for road, work and construction permits
2
Construction
- Clear trees for roads and turbine pads
- Build access roads and pad areas
- Pour the turbine foundation
- Assemble the wind turbine
- Connect to the electrical grid
3
Operation
- Commission the wind turbines to start producing power
- Conduct construction wildlife monitoring
- Monitor remotely for real time alerts when additional maintenance is needed
- Operate for approximately 30 years
4
Decommission or Retrofit
- Assess wind turbine after approximately 30 years
- Decommission wind turbines in 12 months
- Reclaim the site to its former state OR
- Receive approvals and permits to retrofit the turbines to continue harnessing energy
Environmental Impact Assessment
An EIA for the Project was registered with the province on September 5, 2025. To fully assess the potential environmental impacts of the Project, comprehensive studies including the following will be conducted:
Topics of Study:
|
|
|
|
|
|
|
|
|
|
|
|
The Project EIA was submitted on September 3rd 2025. The registration document is available here and is available on the DELG EIA website at the below link:
Sound Levels
The most significant factor when limiting sound impacts to nearby residences is where wind turbines are sited. As such, the wind turbine locations are no closer than 1 km from year-round dwellings. Based on this siting, Natural Forces assessed the impact of sound levels from the Project on nearby residences. This assessment uses industry best practices to model how the sound created by the wind turbines will travel over the landscape.
A third-party consultant reviewed the methodology used to carry out this modelling and to validate the results. The consultants, Aercoustics Engineering, concluded that the methodology used is appropriate and provides conservative results, likely overestimating the expected sound levels.
Results of the modelling indicate that turbine sound levels experienced at nearby year-round dwellings during the Project operation will be below 40 decibels, which is comparable to a soft whisper.
Frequently Asked Questions
Since wind turbines are large mechanical equipment, they can be expected to produce noise. However, as wind turbine technology has evolved, the sound emitted by wind turbines has decreased. In current gearless designs, the mechanical noise is minimal, resulting almost exclusively from the interaction of the air and the turbine blades. This noise decreases as the radial distance from the turbine increases. According to the Government of Nova Scotia, a wind energy project would have a noise level of between 35-45 dB at 350 meters away (Check out the Energy Nova Scotia Wind Page for more information). To relate this, the compressor of a refrigerator produces 40-45 dB of noise. Federal and provincial jurisdictions establish minimum distances from turbines to occupied dwellings to minimize this noise.
A study done by Health Canada in 2014 investigated the health effects of wind turbine noise. This study found that wind turbine noise was not associated with self-reported slip, illness, or stress levels. The summary of these results can be reviewed on the Health Canada Environmental and Workplace Health page.
Shadow flicker is created when the sun is at a certain angle behind the turbine. When the sun shines through the blades, the movement of the blades can cause a shadow that flickers on and off as the blades rotate onto the land. New Brunswick has identified sector specific guidelines for wind turbines that require wind energy projects not to exceed 30 minutes/ day or 30 hours/ year of shadow flicker at any receptor. From initial assessments, the Project is not expected to exceed these thresholds due to the distance from year-round dwellings.
The proposed turbines are set back over a kilometer from year-round dwellings.
The turbines being considered for the Project have a maximum height of approximately 200m to blade tip. Wind turbines have gotten larger over the past few years, allowing them to produce more power and reducing the amount of wind turbines needed to meet energy demands. Though these larger turbines are more efficient and reduce ground disturbance by reducing the number of turbines needed, they are taller and thus can be seen from further areas surrounding the Project. Photomontages will be completed where photos are taken of local areas and with software aid the turbine can be realistically imposed on the photo to provide a general idea of what the landscape will look like once the Project is built.
The Project is proposed on provincial Crown land. While the Project is in operation, the land will still be owned by the province. To own and operate the Project, Natural Forces will obtain a wind power lease, or other necessary real property rights, over the land on which the turbines are located.
Based on data published by the National Renewable Energy Laboratory on the emissions produced within the New Brunswick energy sector alongside a lifecycle carbon emission assessment completed for wind projects in Atlantic Canada, the Project is predicted to offset the carbon that may be emitted during its lifecycle within the first year of operation. This allows at least 29 years of operation to offset emissions produced in the New Brunswick electricity sector from fossil fuel emitting sources.
At wind speeds above 30m/s (108 km/h), the turbine blades feather to not catch the wind and the hub rotates the blade, so they are parallel to wind direction. This causes the turbine blades to reduce their speed drastically to ensure no damage is done to the turbines.
It is estimated that the Project will provide approximately 300 jobs during construction. During construction, Natural Forces and our partners make every effort to hire local contractors. Our in-house construction management company, Natural Forces Construction, is set up to ensure smaller contractors are able to participate.
Natural Forces is aware of snowmobile and hiking clubs in the surrounding area and are committed to working closely with these stakeholders to ensure that impacts to snowmobile and hiking trails are minimized.
For more information please contact:
Jessica Pitman, Project Manager
902-483-9592
community@naturalforces.ca





