Table of Contents

Benjamins Mill Wind Project Future Phase

SHARE

Community Liaison Committee

A Community Liaison Committee (CLC) facilitates communication between project proponents, local community members, and special interest groups throughout the lifetime of a project. Natural Forces is seeking interest in the formation of a CLC for the Benjamins Mill Wind Project to discuss project information and any local ideas and concerns. If you are interested in joining a CLC for the Project in a voluntary capacity, please reach out to us at the contact information below.

 April 2024 Update: 

  • Benjamins Mill Wind Project Phase 2: Natural Forces intends to bid the proposed Phase 2 of the Benjamins Mill Wind Project into the provincial Green Choice Program Request for Proposals. Updates will be posted here on the project website and will be sent to our mailing list, which you can join below. The following notice was sent to members of the surrounding community: November 2023 Green Choice Program Notice

Mailing List

To join the mailing list for the Benjamins Mill Wind Project, please click on the link below and fill out your contact information.

About The Project

This project is located in Mi’kmaki, the ancestral territory of the Mi’kmaq. Natural Forces acknowledges that working on these lands is a privilege that comes with a great deal of responsibility. We believe that private companies have an important role to play in the decolonization of the energy sector and, ultimately, the path towards reconciliation through partnerships and meaningful engagement. To honour and achieve this, we must look forward for generations and integrate the practices and knowledge of the original land stewards, the Mi’kmaq, into project planning.

Phase 1 of the proposed Benjamins Mill Wind Project is being developed by a partnership formed between Natural Forces and Wskijnu’k Mtmo’taqnuow Agency Ltd (the Agency), a corporate body wholly owned by the 13 Mi’kmaw bands in Nova Scotia. Together, the partnership will develop, construct, operate, and own the 8 turbine first phase of the project. The project is located in the West Hants Regional Municipality in Hants County, 14 km southwest of Windsor.

The project is proposed to be built in several phases. As such, the project could have an approximate total capacity of 150 MW, representing up to 28 turbines that could collectively power up to 58,000 Nova Scotian homes.

Phase 2: Future phases of the Benjamins Mill Wind Project will be proposed as part of new procurement programs for wind energy projects in Nova Scotia. The project partners intend to bid Phase 2 of the project into the upcoming provincial Green Choice Program Request for Proposals to secure a power purchase contract. This type of contract is necessary for additional project phases to be built. The most up-to-date information on the program can be found on their website, here.

Proposed Project Layout: Phase 2 

Below is a map of the proposed Benjamins Mill Wind Project layout, showing both Phase 2. This includes the road and turbine layout included in the Environmental Impact Assessment alongside 1 km setback buffers from all nearby residences.

Project Timeline

  • September 2020 – Wind data collection began on site
  • February 2021 – Private site lands secured under contract
  • March 2021 – Environmental studies began
  • July 2021 – First public open house hosted at the South West Hants Fire Hall
  • August 2021 – Work with West Hants Regional Municipality staff on the Development Agreement application began
  • January 2022 – Environmental Assessment (EA) submitted to the Nova Scotia Department of Environment and Climate Change
  • February 2022 – Second public open house hosted online
  • October 2022 – Third public open house hosted at the South West Hants Fire Hall
  • January 2023 – Addendum to the EA was submitted to the Nova Scotia Department of Environment and Climate Change
  • February 2023– EA approval received from the Minister of the Nova Scotia Department of Environment and Climate Change
  • April 2023 – Fourth public open house hosted at the South West Hants Fire Hall
  • August 2023 – Public hearing and successful second reading of the Development Agreement at the West Hants Council meeting
  • November 2023 – Notice sent to community members of Natural Forces’ intention to bid Phase 2 of the project into the Green Choice Program
  • May 2024 – Fifth public open house hosted at the South West Hants Fire Hall
  • June 2024 – Phase 2 to be bid into the provincial Green Choice Program request for proposals (GCP RFP)
 

Who is proposing this project?

Phase 1 of the Benjamins Mill Wind Project is being constructed, and will be owned and operated, by a partnership between Wskijnu’k Mtmo’taqnuow Agency and Natural Forces. The proposed Phase 2 of the Benjamins Mill Wind Project is being developed, and will be constructed, owned, and operated by Natural Forces.

Wskijnu’k Mtmo’taqnuow Agency Limited (The Agency)

The Agency is a corporate entity created by the 13 Mi’kmaw bands in Nova Scotia, which was created to develop partnerships with industry leaders.

Recognizing the need to build capacity and work with experts to participate in opportunities happening in Mi’kmaki, the 13 bands created the Agency to pursue and manage business opportunities for the Mi’kmaq Nation.

The Agency is overseen by a five member board, that is currently comprised of three Chief nominated members’ board seats and two seats filled by community members. The board’s responsibilities include meeting with companies to evaluate potential partnership opportunities and managing these ongoing relationships. In addition to the Board, the Agency has shareholder seats that are filled by the Chiefs of the 13 bands.

Natural Forces

Natural Forces is an independent power producer that develops, owns, and operates renewable energy projects. Natural Forces was established in 2001 and has its head office in Halifax, NS, as well as regional offices in Chetwynd, British Columbia; Quispamsis, New Brunswick; and Dublin, Ireland. Collectively, Natural Forces has close to 300 MW of renewable energy projects in operation across Canada, with several ongoing projects at various stages of completion in Nova Scotia, New Brunswick, Prince Edward Island, Labrador, Saskatchewan, British Columbia, and Ireland.

The senior management team at Natural Forces has over 70 years of combined renewable energy experience encompassing all project life cycle activities in a range of international locations including Canada, Ireland, Poland, the UK, and Australia. Natural Forces is an integrated developer and operator of renewable energy assets. The in-house team undertakes all activities from initial site selection, development, financing, construction, operations, and asset management. Our vision is to develop, construct, operate, and own clean renewable energy projects across Canada in partnership with local and Indigenous communities.

Why here?

When developing a wind project, it is crucial to find the most suitable location and community to host it. To do so, there are four main factors to consider during the site-finding phase of development:

  • Wind resource
  • Distance to existing electrical and civil infrastructure
  • Environmental sensitivity
  • Socio-economic concerns

Nova Scotia has excellent wind resources, so generating electricity is feasible in many locations around the province. Factors other than the strength and consistency of the wind must be taken into account when considering a site, such as proximity to the electricity grid, road access, ecology, archaeology, and cultural significance, proximity to residential dwellings, and health concerns.

The location of the proposed Benjamins Mill Wind Project was selected after a thorough review of all of these factors.

Stakeholder Engagement

Natural Forces is committed to engaging with all stakeholders and stakeholder groups throughout the lifetime of the project. We are both keen to ensure the community understands the project details and is aware of project activities, and to accept input and feedback from community members. Below is information about the major public and stakeholder engagement activities that have taken place to date, including summaries of the information that has been shared at our open houses.

​The development of wind energy in Nova Scotia provides a clean and stable source of energy that displaces energy generated from fossil fuels. Wind energy development positively impacts the community in a variety of ways, including:

  • Providing tax revenue to the hosting municipality for the entire lifetime of the project;
  • Creation of local employment and contracting opportunities during all phases of the project;
  • Stabilizing energy costs for Nova Scotia Power customers by increasing electricity generation sources with fixed cost contracts; and,
  • Increased revenue to local businesses due to economic spinoff from project activities.

Newsletters

Natural Forces has engaged with, and continues to engage with, stakeholders through a number of avenues, including newsletters. Each of the newsletters circulated to date are linked below:

Open Houses

Natural Forces has held five public open houses to provide opportunities for the community to engage with Natural Forces staff. The first, third, fourth, and fifth open houses were held in person, while the second was held online due to COVID-19 restrictions. All of the information that was presented at each of these open houses is linked below:

Natural Forces will continue to host open houses throughout the development of the project.

Based on feedback received and requests made at our open houses, we have prepared the following materials:

What is the process?

1

Development
(Current Stage)

  • Assess the wind resource
  • Survey for environmentally sensitive features
  • Optimize turbine location to capture the wind efficiently and minimize impact on sensitive features
  • Begin consultation with regulators and the public
  • Conduct and present the Environmental Impact Assessment for environmental approval
  • Apply for road, work and construction permits​

2

Construction

  • Clear trees for roads and turbine pads​
  • Build access roads and pad areas
  • Pour the turbine foundation
  • Assemble the wind turbine
  • Connect to the electrical grid

3

Operation

  • Commission the wind turbines to start producing power
  • Conduct post-construction wildlife monitoring
  • Monitor remotely for real time alerts when additional maintenance is needed
  • Operate for 30 years​

4

Decommission or Retrofit

  • Assess wind turbines after 30 years
  • Decommission wind turbines in 3-6 months
  • Reclaim the site to its former state OR
  • Receive approvals and permits to retrofit the turbine to continue harnessing energy​

Mi’kmaq Ecological Knowledge Study 

The project partners hired the company Membertou Geomatics to complete a Mi’kmaq Ecological Knowledge Study (MEKS) for the Project area. Scoping for the MEKS began in 2021 and the studies were completed in 2022. The final report was prepared and then reviewed by  and the final report was reviewed by Kwilmu’kw Maw-klusuaqn (KMKNO) in 2023. By adhering to the Mi’kmaq Ecological Knowledge Study Protocol, 2nd Edition (2014), this study identifies traditional and current Mi’kmaq uses of the land in the vicinity of the Project and incorporates a Mi’kmaq Significant Species Analysis.

The full MEKS can be found below

Benjamins Mill Wind Project Mi’kmaq Ecological Knowledge Study

Environmental Impact Assessment

In Nova Scotia, any wind projects that exceed 2 MW in size are required to complete a provincial environmental impact assessment (EIA). During this process, an entire committee made of provincial and federal agencies evaluates the location and overall impact of the project on the surrounding environment and the public. As the proposed Benjamins Mill Wind Project would produce up to approximately 150 MW of electricity, it is subject to an EIA.

To fully assess the potential environmental impacts of the project, the following comprehensive studies have been conducted:

  • Wind Resource Assessment
  • Wetlands and Watercourses Surveys
  • Bird and Bat Surveys
  • Vegetation and Habitat Surveys
  • Noise and Visual Assessments
  • Radiocommunication Impact Assessments
  • Archaeological Assessments
  • Geological Surveys

The results from these studies are compiled in the EIA document that was registered with the province on January 18, 2022. As is common with projects of this kind, the Minister of the Department of Environment and Climate Change requested additional information to provide a final decision on the project. As such, the environmental studies at the project site have continued in 2022, the results of which were compiled and reported on in the addendum to the initial registration document. As of February 13, 2023, the Benjamins Mill Wind Project’s environmental assessment has been approved by the Minister of Environment and Climate Change.

More information on the EIA can be found below, or on the provincial EIA website. Both the initial EIA document (2022) and the addendum (2023) can also be viewed below.

Questions from the Open Houses

In order to finance and build this project, a power contract is required. These two provincial programs are opportunities to obtain a power contract. If we are not selected for the Rate Base Procurement or the Green Choice Program, we will need to wait for other opportunities in the future.

We do not receive comments submitted through the government’s website as a default – however, we are committed to obtaining any questions asked. You can also submit your questions directly to us by using the contact details at the bottom of the page.

We did not, but we have taken note of this and will investigate further

Seeing as this site is previously disturbed by forestry activities, there is an existing network of access roads. We will be trying to use these roads as much as possible, and will perform upgrades to those that we will be using. However, some new roads will need to be constructed to access the turbine locations. The final road layout will be made available as soon as the project layout is finalized.

Yes – we are committed to providing additional visualizations of what the project is expected to look like from Falls Lake and other landmarks near the project site, as well as a map showing how much of the project area will be cleared.

A third-party noise validation assessment is being performed by Aercoustics.

The layout is not finalized at the moment, and a lot can change between now and construction. All comments on the layout will be taken into consideration when finalizing the design.

We are doing out due diligence to ensure that this project is developed and sited responsibly. This includes meeting and exceeding the industry setbacks. We have also conducted sound and visual studies that will be validated by a third party. These studies show that, given the worst-case scenario (i.e., climatic conditions, wind in all directions, no obstacles blocking sound and light, etc.), very minimal sound and shadow-flicker is expected to reach the nearest homes.

We are actively seeking to build relationships with community members and will continue to do so.

Frequently Asked Questions

Natural Forces undertakes rigorous environmental impact assessments ahead of construction to determine existing environmental sensitivities and potential impacts on the project to the environment. This information will be reviewed by provincial government officials and will be open for public comment.

The proposed turbines will be set back at least 1.0 km from all cabins and houses.

Are wind turbines bad for my health? ​A study done by Health Canada in 2014 investigated the health effects of wind turbine noise. This study found that wind turbine noise was not associated with self-reported sleep, illness or stress levels. The summary of these results can be reviewed on the Health Canada Environmental and Workplace Health page and links to additional studies can be found in the following section.

For this project, Natural Forces leased land from private landowners and has made agreements with the provincial government for Crown land. Over the course of several years, we have developed trusted relationships with the landowners and in all instances the land remains in the ownership of the landowner and is leased for the duration of the project. No land has been leased from unwilling landowners.

During construction, Natural Forces makes every attempt to hire local contractors, using our in-house construction management company, Natural Forces Construction, to ensure smaller contractors are able to participate. 

Wind turbines have moving parts and therefore some sound can be expected. However, well-designed wind turbines are generally quiet in operation, and compared to the noise of road traffic, trains, aircraft, and construction activities, the sound from wind turbines is very low. As wind turbine technology has evolved, the sounds emitted have decreased. The further away you are from a project, the less sound it will make. This site will likely have trees and other barriers that would break a lot of the sound before it reaches homes. A typical wind project would have a noise level of between 35-45 decibels. For reference, the compressor of a refrigerator produces 40-45 decibels. (Check out the Energy Nova Scotia Wind Page for more information). Stories of excessive noise often come from areas where the turbines are very close to homes. Natural Forces follows the minimum standards for distance from residences laid out by local regulations, or a typical minimum of 1KM.

For more information contact:

Meg Morris, Project Manager
902-483-9592
community@naturalforces.ca

MORE PROJECTS

The initial plans are for the proposed project to consist of an estimated 10-12 wind turbines that will have an installed capacity of approximately 50 MW, enough electricity to power over 17,000 Nova Scotian homes. The project is located in Cumberland County, on Westchester Mountain near Highway 104, approximately 24 km from the Cobequid Pass Tolls.
Welcome to the website for the proposed Wejipek Wind Project! This website was created to provide information to community members, First Nations, government, and other stakeholders about the proposed project. Natural Forces is committed to meeting with stakeholders throughout the lifetime of the project. Open houses and other community engagement activities are planned for this project - the website will be updated as information becomes available.
Welcome to the website for Phase II of the Wocawson Energy Project! This phase has been named the Neweg Energy Project. This website was created to provide information to community members, First Nations of New Brunswick, the government, and other stakeholders about the project. Natural Forces is committed to meeting with rightsholders and stakeholders throughout the lifetime of the project.
This project is located in Mi’kmaki, the ancestral territory of the Mi’kmaq. Natural Forces acknowledges that working on these lands is a privilege that comes with a great deal of responsibility. We believe that private companies have an important role to play in the decolonization of the energy sector and, ultimately, the path towards reconciliation through partnerships and meaningful engagement. To honour and achieve this, we must look forward for generations and integrate the practices and knowledge of the original land stewards, the Mi’kmaq, into project planning.
The proposed Benjamins Mill Wind Project is being developed by a partnership formed between Natural Forces and Wskijnu’k Mtmo’taqnuow Agency Ltd (the Agency), a corporate body wholly owned by the 13 Mi’kmaw bands in Nova Scotia. Together, the partnership will develop, construct, operate, and own the project. The project is located in the West Hants Regional Municipality in Hants County, 14 km southwest of Windsor.
The proposed Benjamins Mill Wind Project is being developed by a partnership formed between Natural Forces and Wskijnu’k Mtmo’taqnuow Agency Ltd (the Agency), a corporate body wholly owned by the 13 Mi’kmaw bands in Nova Scotia. Together, the partnership will develop, construct, operate, and own the project. The project is located in the West Hants Regional Municipality in Hants County, 14 km southwest of Windsor.